Oxford City Council and Peabody are working together to bring 294 new affordable homes, shops, green spaces and a new Community Centre to Blackbird Leys.

The project is focused on the District Centre (including the ‘top shops’ and Blackbird Leys Community Centre) and land between Knights Road and the Kassam Stadium.

Find out the latest

We started construction at the end of 2023.  This was after we received planning permission from the council in summer 2023.

Our contractor, Hill is carrying out building work on sites near Evenlode Tower, Windrush Tower, and on Knights Road.

How you can get involved

Are you interested in working on the Blackbird Leys redevelopment project or learning skills in construction? We’ll soon be setting out how the local community can get involved. Find out more in the newsletter in the download link below.

The Community Centre

We have now finalised designs for the new Community Centre, and have submitted a detailed planning application to Oxford City Council.

We have worked with local community to develop the designs and want to thank everyone for your input and involvement.

Download the latest newsletter

What’s going on this month?

  • Block A: we are waiting for approval from the Building Safety Regulator to begin further work – we expect this by the end of November
  • Block D: we will progress above ground construction including installing steel and concrete structures
  • Knights Road: work continues on the first 28 houses and foundation and drainage work.

Highways work

Highways work at the District Centre started in November following an agreement with Oxfordshire County Council.

In the first phase we will start to create new foot and cycle paths.  We expect this phase to last seven weeks and finish in December.

Barriers have been put around the central green (coloured in light orange on the map below) and we have set up temporary traffic lights.  The parking bays opposite the shops are unavailable as works progress.  There will also be utilities diversion work for electricity and BT and Virgin users.

We will continue to share updates on upcoming highways work as the programme progresses.

Map showing Phase 1 of the highways works

When will construction be complete?

  • Block A – at the end of 2026
  • Block D – in January 2026
  • Knights Road – by April 2026, with handovers on houses starting in June 2025.